Saturday, January 28, 2012

January 10 - January 27, 2012

The laminate counter tops were installed.
Below is the main upstairs bath.
Below is one of the kids sinks.
Below is the laundry room counter top.
The garage was taped and mudded.
They began the stair banister.
They began the fireplace surround.
The island cabinets were installed.
The Master Bathroom tile was installed.
More Fireplace.
More Master Bathroom tile.
More fireplace.
Finished Stair Banister (it still needs to be stained)
The outside woodwork was completed.
Finished Fireplace
Our air conditioner was installed.
Our appliances were delivered.


All of the doors were painted.
The pantry was painted.
The granite and cooktop was installed.





It's looking like we'll be able to move in around February 23rd. Yeah!!!

Monday, January 9, 2012

January 1st, 2012 through January 9, 2012

January 1, 2012 - They started putting up the white trim.
January 4, 2012 - They primed all the walls in the house. I had to pick three colors. That was hard. Then when I came in, most of the rooms were primed the wrong colors. Then, when I came back the next day they had all been fixed.
January 5, 2012 - The wood floors were installed.
January 6, 2012 - They started the siding.
January 9, 2012 - They started installing the kitchen cabinets and some of the trim.

December Epic House Update

December 1, 2011 - The fireplace was installed.
December 5, 2011 - The front porch was poured.
December 7, 2011 - They started insulating.
December 13, 2011 - They started dry walling.
(Dave's Office)
(looking through the dining room from the foyer to the kitchen)
(the great room)
(the kitchen)
(the laundry room)
(the garage)
(the staircase - looking up from the great room)
(the play room)
(my craft room/office)
(the upstairs hallway)
(Madison's bedroom)
(Gabe's bedroom)
(Our bedroom)

(Our bathroom)